PROJECT LIMITS
This project
proposes to widen approximately 1.3 miles of the existing
two-lane Capital Circle SE from west of Woodville
Highway to west of Crawfordville Road to a multi-lane
urban principal arterial.
View Project Map
PROJECT PURPOSE
Improve Capital Circle SE,
from Apalachee Parkway to Crawfordville Road, to a
controlled access facility with major intersection
improvements at Midyette Road, Blair Stone Road, and
SouthWood Plantation entrances, Tram Road; Woodville
Highway; and Crawfordville Road.
A construction alternative
exists that would provide four through lanes in the
interim (at a cost of $10 Million). The roadway would
operate at an acceptable level of service for over
10 years, at which time the additional lanes could
be constructed.
The project design
includes an urban typical section consisting of three
12-foot travel lanes in the eastbound direction and
four 12-foot travel lanes in the westbound direction
utilizing a 36-foot grass median. The typical section
includes a 4-foot bicycle lane in each direction with
a 5-foot sidewalk and 10-foot meandering sidewalk
located on the southside and northside of the roadway,
respectively. The project includes curb and gutter,
stormwater improvements and landscaped median and
borders. The posted speed limit will be 45 mph.
The major construction
activities associated with the proposed improvements
involve the following:
• Addition of
thru lanes and signal upgrades at major intersections;
• Capability
to expand or add transit, multi-modal and pedestrian
improvements along the existing corridor;
• Connections
from sidewalks and bicycle lanes along Capital Circle
to the St. Marks multi-use trail;
• Installation
of new drainage facilities;
PROJECT SCHEDULE
The project is currently at
60% in the design phase and on hold awaiting future
funding. Right-of-Way maps are at 100%. Blueprint
2000 is in the position to begin acquiring Right-of-Way
as funding becomes available. Neither Right-of-Way
nor construction phases for this project are currently
included within the Master Plan; however, Blueprint
2000 is seeking to leverage its funding by applying
for Transportation Regional Incentive Program (TRIP)
funding and other federal and state transportation
funding programs.
PROJECT COST
Right-of-Way and Construction
costs are estimated to be $25 million for the full
project. The interim four lane design can be built
for approximately $10 Million.
PROJECT OWNER
Florida Department of Transportation
and Blueprint 2000 Intergovernmental Agency.
MANAGEMENT:
Blueprint 2000
CCSE – WOODVILLE
HIGHWAY TO CRAWFORDVILLE ROAD CONTACT PERSONNEL
Blueprint 2000 &
Beyond
1311 Executive Center Drive, Suite 109
The Koger Center, Ellis Building
Tallahassee, FL 32301
Tel: 850.701.2740
Fax: 850.701.2790
Gary
Phillips, Project Manager:
Gary.Phillips@blueprint2000.org