PROJECT PURPOSE:
To improve safety and traffic
flow efficiency; the Florida Department of Transportation
(FDOT) widened Capital Circle Northwest from Commonwealth
Lane to West Tennessee Street from three lanes to
six lanes. The project required the construction of
a regional stormwater facility south of West Tennessee
Street. The contribution of Blueprint 2000 to this
joint venture and in conjunction with the Blueprint
philosophy, the facility was designed as a multi use
pond. The facility provides improved stormwater treatment
and reduces downstream flooding. View
project map.
PROJECT LIMITS:
Project limits were from Commonwealth
Lane to West of Tennessee Street on Capital Circle Northwest.
This 1.991-mile roadway project consisted of upgrading
the intersections to the West Tennessee Street, Tharpe
Street, Hartsfield Road and Commonwealth Lane.
View Project Map
PROJECT SCHEDULE:
Construction began in late 2005
and was completed in September 2007.
PROJECT OWNER:
Blueprint 2000 & Beyond
Intergovernmental Agency / Florida Department of Transportation.
PROJECT COST:
$25.5 Million
CAPITAL CIRCLE SOUTHWEST CONTRACTOR INFORMATION:
The roadway project was designed,
let and constructed by the Florida Department of Transportation,
with advance funding provided by the Blueprint 2000
Intergovernmental Agency. M of Tallahassee, Inc. was
the contractor that performed the work.
CONSTRUCTION ENGINEERING &
INSPECTION:
PBS&J managed the daily
operations of the project for Blueprint 2000.
Blueprint 2000 & Beyond
1311 Executive Center Drive,
Suite 109
The Koger Center, Ellis Building
Tallahassee, FL 32301
Tel: 850.701.2740